Risk Management Planning Exercise

profilenyc0613
  • Schedule Compression and Resource Leveling (100 points)
  • This assignment consists of 3 parts: questions about resourcing projects, schedule development and compression, and resource leveling. 
  • Part 1 Questions (20 points)
  • Provide responses to the following questions
  • 1.    What is the purpose of a staffing management plan?  What does it address?
  • 2.    Whom should the project manager consult when performing resource leveling?
  • 3.    Describe the two primary techniques for compressing a schedule?
  • 4.    When crashing a project schedule, describe the two criteria that are considered when considering which activities will be sped up.
  • Part 2 Project network/schedule -scheduling and compressing a schedule (30 points)
  • You’ve been asked to manage a project that includes conducting a two-week (10 working days) computer training class. Using the information in Table below, complete the following:
  • Activity
  • Immediate Predecessor
  • Normal Time (days)
  • Normal Cost
  • Crashed Time (days)
  • Crashed Cost
  • A – Obtain Instructor
  • None
  • 7
  • $500
  • 4
  • $800
  • B – Locate Room
  • A
  • 3
  • $200
  • 2
  • $350
  • C – Check Coats
  • None
  • 6
  • $500
  • 4
  • $900
  • D – Room Open?
  • C
  • 3
  • $200
  • 1
  • $500
  • E – Schedule Class
  • B and D
  • 2
  • $300
  • 1
  • $350
  • Prepare a network schedule showing:
  • Early Starts (ES) for all activities
  • Late Starts (LS) for all activities
  • Slacks for all activities
  • Critical path and its length
  • Non-critical paths and their length
  • Schedule Compression:
  • What is the crash cost per day for each activity?
  • Which activities should be crashed to meet a project deadline of 10 days with a minimum cost? You may assume that you can partially crash an activity.
  • What is the new cost after crashing the project?
  • Fully crash the project to its minimum duration.  Prepare a table that shows (for each day the project length is reduced) the project duration, the activities that are crashed, the incremental crash cost, and the total crash cost.
  • Part 3 Resource Leveling (40 points)
  • Using the data below
  • Activity ID
  • Activity
  • Immediate Predecessor
  • Duration in days
  • Resource
  • Work Hours per Day
  • A
  • Evaluate freezers
  • 2
  • Alcides
  • 6
  • B
  • Chart temperatures
  • 6
  • Joan
  • 4
  • C
  • Review service record
  • 2
  • Alcides
  • D
  • Consult with HVAC engineer
  • A, B, C
  • 3
  • Alcides
  • E
  • Develop construction plan
  • D
  • 10
  • Joan
  • F
  • Complete IC assignment
  • E
  • 2
  • Alcides
  • G
  • Complete ROI analysis
  • E
  • 5
  • Joan
  • H
  • Conduct regulatory review
  • E
  • 4
  • Joan
  • I
  • Obtain construction approval
  • F, G, H
  • 2
  • Alcides
  • a.    Create a project schedule in MS Excel ensuring that it reflects the predecessor/successor relationships identified in the table.
  • b.    How long will it take to complete the project?
  • c.    Joan and Alcides are not fully dedicated to the project.  Joan is only available for 4 hours each day, and Alcides is available for 6 hours per day.  The original estimated duration (in 8-hour days) results in over-allocation of Joan and Alcides.  Prepare a resource-leveled project schedule in MS Excel.  How long will it take to complete the project in a resource-leveled environment?
  • Posted: 2 years ago
  • Due: 
  • Budget: $15
Answers 2
  • Risk Management Planning Exercise
    Answer rating:4Stars out of1ratings

Purchase the answer to view it

blurred-text
  • 0

Purchase the answer to view it

blurred-text
    • Rated 1 times

      Exercise

      Complete Chapter 9 Exercise Questions #1, #2 and #3 on page 322 of the Kloppenborg (2019) textbook.

    • Describe at least three approaches that project managers can use to build individual and project team capability.

      The assignment is to answer the question provided above in essay form. This is …

    • Reflect on the assigned readings for Week 2 and then type a two page paper regarding what you thought was the most important concept(s),method(s),term(s),and/or any other …

    • Identify and describe the three steps that the team should follow in order to define project scope and create a project scope statement.

      Submit APA formatted document

      The assignment is to …

    • Part 1)

      Read“Suburban Homes Construction Project”at the end of Chapters 4 and 5 (in the textbook) and then answer the questions at the end of the reading.

      Submit your …

    • Part1)


      Read“Suburban Homes Construction Project”at the end of Chapters 12 and 13 (in the textbook) and then develop a quality management plan.

      Submit your …

    • Rated 1 times

      Research paper

      Please see the Research project attachment for instructions. This is Due on 27Feb2020.

    • Reflect on the assigned readings for Week 2 and then type a two page paper regarding what you thought was the most important concept(s),method(s),term(s),and/or any other …

    • Reflect on the assigned readings for Week 3 and then type a two page paper regarding what you thought was the most important concept(s),method(s),term(s),and/or any other …

    • Reflect on the assigned readings for Week 1 and then type a two page paper regarding what you thought was the most important concept(s), method(s), term(s), and/or any other thing that you felt was …