Risk Management Planning Exercise

profilenyc0613
  • Schedule Compression and Resource Leveling (100 points)
  • This assignment consists of 3 parts: questions about resourcing projects, schedule development and compression, and resource leveling. 
  • Part 1 Questions (20 points)
  • Provide responses to the following questions
  • 1.    What is the purpose of a staffing management plan?  What does it address?
  • 2.    Whom should the project manager consult when performing resource leveling?
  • 3.    Describe the two primary techniques for compressing a schedule?
  • 4.    When crashing a project schedule, describe the two criteria that are considered when considering which activities will be sped up.
  • Part 2 Project network/schedule -scheduling and compressing a schedule (30 points)
  • You’ve been asked to manage a project that includes conducting a two-week (10 working days) computer training class. Using the information in Table below, complete the following:
  • Activity
  • Immediate Predecessor
  • Normal Time (days)
  • Normal Cost
  • Crashed Time (days)
  • Crashed Cost
  • A – Obtain Instructor
  • None
  • 7
  • $500
  • 4
  • $800
  • B – Locate Room
  • A
  • 3
  • $200
  • 2
  • $350
  • C – Check Coats
  • None
  • 6
  • $500
  • 4
  • $900
  • D – Room Open?
  • C
  • 3
  • $200
  • 1
  • $500
  • E – Schedule Class
  • B and D
  • 2
  • $300
  • 1
  • $350
  • Prepare a network schedule showing:
  • Early Starts (ES) for all activities
  • Late Starts (LS) for all activities
  • Slacks for all activities
  • Critical path and its length
  • Non-critical paths and their length
  • Schedule Compression:
  • What is the crash cost per day for each activity?
  • Which activities should be crashed to meet a project deadline of 10 days with a minimum cost? You may assume that you can partially crash an activity.
  • What is the new cost after crashing the project?
  • Fully crash the project to its minimum duration.  Prepare a table that shows (for each day the project length is reduced) the project duration, the activities that are crashed, the incremental crash cost, and the total crash cost.
  • Part 3 Resource Leveling (40 points)
  • Using the data below
  • Activity ID
  • Activity
  • Immediate Predecessor
  • Duration in days
  • Resource
  • Work Hours per Day
  • A
  • Evaluate freezers
  • 2
  • Alcides
  • 6
  • B
  • Chart temperatures
  • 6
  • Joan
  • 4
  • C
  • Review service record
  • 2
  • Alcides
  • D
  • Consult with HVAC engineer
  • A, B, C
  • 3
  • Alcides
  • E
  • Develop construction plan
  • D
  • 10
  • Joan
  • F
  • Complete IC assignment
  • E
  • 2
  • Alcides
  • G
  • Complete ROI analysis
  • E
  • 5
  • Joan
  • H
  • Conduct regulatory review
  • E
  • 4
  • Joan
  • I
  • Obtain construction approval
  • F, G, H
  • 2
  • Alcides
  • a.    Create a project schedule in MS Excel ensuring that it reflects the predecessor/successor relationships identified in the table.
  • b.    How long will it take to complete the project?
  • c.    Joan and Alcides are not fully dedicated to the project.  Joan is only available for 4 hours each day, and Alcides is available for 6 hours per day.  The original estimated duration (in 8-hour days) results in over-allocation of Joan and Alcides.  Prepare a resource-leveled project schedule in MS Excel.  How long will it take to complete the project in a resource-leveled environment?
Answers 2
  • Risk Management Planning Exercise
    Answer rating:4Stars out of1ratings

Purchase the answer to view it

blurred-text
  • 0

Purchase the answer to view it

blurred-text
    • Rated 1 times

      Exercise

      Complete Chapter 9 Exercise Questions #1, #2 and #3 on page 322 of the Kloppenborg (2019) textbook.

    • Rated 1 times

      Unit 9 - PM

      Discussion Forum (suggested level of effort: 1 hour)

      The purpose of a discussion forum is for students to engage one another over topics related to the course material. An initial post by …

    • Part 1)

      Read“Suburban Homes Construction Project”at the end of Chapters 4 and 5 (in the textbook) and then answer the questions at the end of the reading.

      Submit your …

    • Rated 1 times

      Exercise

      Complete Exercise Questions #1 and 2 on page 352 of Kloppenborg text (attached text book)



    • Part1)


      Read“Suburban Homes Construction Project”at the end of Chapters 12 and 13 (in the textbook) and then develop a quality management plan.

      Submit your …

    • Reflect on the assigned readings for Week 2 and then type a two page paper regarding what you thought was the most important concept(s),method(s),term(s),and/or any other …

    • Part 1)

      Read “Suburban Homes Construction Project” at the end of Chapters 14 and 15 (in the textbook) and then develop a communication plan.

      Submit your answer …

    • Reflect on the assigned readings for Week 1 and then type a two page paper regarding what you thought was the most important concept(s), method(s), term(s), and/or any other thing that you felt was …

    • Question: To help identify risks, what are some questions a project manager could ask when reviewing the project charter and WBS?


      Instructions: This question involves the student posting a …

    • Rated 1 times

      Exercise

      Complete Chapter 8 Exercise Questions #2 through #8 on page 278 of the Kloppenborg text. The length of the paper should be enough pages to properly and fully answer all the exercise questions. …