PROBLEM 1:  CALCULATE SCHEDULE VARIANCE FROM EARNED VALUE CALCULATIONS FROM A 4 MONTH PERIOD.


PLANNED VALUE (PV):  38


EARNED VALUE (EV):  30


CALCULATE SCHEDULE PERFORMANCE INDEX:


CALCULATE ESTIMATED TIME TO COMPLETION:



PROBLEM 2:  CALCULATE COST VARIANCE FROM EARNED VALUE CALCUATIONS  WHERE PV = 38.


ACTUAL COST OF WORK PERFORMED (AC):  $40,000


EARNED VALUE:  30


CALCULATE COST PERFORMANCE INDEX:


CALCULATE ESTIMATED COST TO COMPLETION:


 

 Show your complete  work with formulas and equation (calculations). Without complete and very step calculations and substitution of showing formulas and calculations, your assignment would be considered zero.