Calculate the total volume of excavation

profileSadeen Alharbi

The site is required to be reduced to a level of Zero. Calculate the total volume of excavation? 

Assume the cost of excavation (direct cost) is 15 SR per 1 m3 (this cost only includes the equipment and labor prices) 

Calculate the direct cost, then calculate the indirect cost which includes the overheads, contingency and profit. After that calculate the direct and indirect cost. (4 marks)

  • VAT 15%
  • Overheads 10%
  • Contingency 6%
  • Profit 12.5%