unit II mini project (let me know if you need any thing else from me to complete this)

profilema2211
UnitIIMEE6501-18H-5B20-S1AdvancedAirQuality....html

Open Quick Links

Quick Links

Page Landmarks

    Content Outline

      Keyboard Shortcuts

        Logout Global Menu Michael AdamsActivity UpdatesExpand Global Nav
        Columbia Southern University

        Top Frame Tabs

        Home Tab 1 of 3 (active tab) Notifications Tab 2 of 3 My Community Tab 3 of 3

        Current Location

        1. MEE 6501-18H-5B20-S1, Advanced Air Quality Control Course-to-Course Navigation
        2. Unit II
        Hide Course Menu

        Menu Management Options

        Course Menu:

        MEE 6501-18H-5B20-S1, Advanced Air Quality Control

        Course Entry Page

        Unit II

        Content

        • Item

          Unit II Intro – Atmospheric Effects

          Unit 2 goes into a deeper discussion on the topic of atmospheric effects.  The conditions that impact visibility comparing factors that produce hazy conditions and pristine air.  The topic of stratospheric ozone depletion is presented along with the topic of global warming.  Today this might be better described as a component of climate change. The unit has a discussion board and a mini project for the assessment.

        • Web Link

          Unit II Study Guide

        Click the link above to open the unit study guide, which contains this unit's lesson and reading assignment(s). This information is necessary in order to complete this course.

        • Discussion Board

          Unit II Discussion Board

          Unit II Discussion Board Open

          • Weight: 2% of course grade
          • Grading Rubric
          • Response Due: Saturday, 04/04/2020 11:59 PM (CST)
          • Comment Due: Tuesday, 04/07/2020 11:59 PM (CST)

          Go to Unit II Discussion Board »

        • Assignment

          Unit II Mini Project

          Unit II Mini Project Open

          • Weight: 10% of course grade
          • Grading Rubric
          • Due: Tuesday, 04/07/2020 11:59 PM (CST)
          Instructions

          Over the course of the next six units, you will be developing a course project. You will complete a single section of the course project in every unit by completing one section of the course project, and then you will add to it with the subsequent work in the following unit. This unit work will be in the form of unit mini projects.

          Our course project will be to develop a document titled “A Permit by Rule (PBR) Evaluation for a Painting Operation” and will serve as a simulation of our work as a contract environmental engineer to an industrial organization planning a painting operation within the United States.

          The Scenario:

          You have contracted with an industrial organization to engineer and write a state air Permit by Rule (PBR) evaluation for a painting operation facility. According to the local state laws and U.S. Environmental Protection Agency (EPA) laws, the facility must have an air permit before construction begins. Once the facility is completed, the construction air permit will then become the operational air permit for the facility.

          As a result, your client wants the air permit to automatically align the painting operation facility into operational compliance with state and federal air quality laws. Consequently, it is extremely important for you to evaluate the planned painting operation against the PBR requirements in order to meet the air permit criteria, using the state guidance document and considering the equipment and chemicals already planned for the facility operations.

          You have tabulated the following information from what you have gleaned from the material SDS documents and equipment technical data sheets plan (depending on your scenario selection, each “unit” represents a single aircraft, rail tank car, or vehicle):

          Interior Liner Coating Material

          10 gallons coating/unit

          2 gallons of solvent/unit

          Unit Lining Application

          Apply interior liners to two (2) units/day

          Work five (5) hours/day and four (4) days/week

          Unit Lining Curing

          Cure interior liners of two (2) units/day

          Work five (5) hours/day and four (4) days/week

          Interior Liner Cure

          Heater fuel source is natural gas-fired drying oven

          Heater generates 2.1 million (MM) Btu/hr at maximum 2,500 hrs/year

          Unit Lining Design

          Cross-draft air plenum

          Unit interior is the spray area

          Exhaust Fan

          10,000 ft3/min (CFM)

          1 exhaust fan

          Air Makeup Unit

          5760 ft3/min (CFM)

          1 air makeup system

          Filter Openings

          20.0 ft2 each

          Two (2) filter openings

          Coating WV

          VOC content

          2.8 lb/gal coating

          Coating VM

          Coating volume

          1.0 gal

          Water Content

          Per gal/coating

          1.0 lb/gal

          Water Density

          Per gal/water

          8.34 lb/gal

          Coating VW

          Water volume

          Calculation

          Exempt-solvent Content

          Per gal/coating

          0.5 lb/gal

          Exempt-solvent Density

          Per gal/exempt solvent

          6.64 lb/gal

          Coating Ves

          Exempt solvent volume

          Calculation

          Additionally, your state’s department of environmental quality (DEQ) has provided you the following PBR limits:

          Potential to Emit (PTE) 100 tons VOC/year
          Face Velocity 100 ft/min
          Filter Velocity 250 ft/min
          VOC/5-hour period 6.0 lbs/hr
          Short-term Emissions 1.0 lbs/hr
          Long-term Emissions 1.0 tons/yr

          From your first visit with your client, these are your notes and process flow sketch reflecting the intended operational design:

          • The client has designed an interior coating spray painting system that allows the interior of each unit to be coated.
          • The operations will involve a stripped-down unit being brought into the facility’s shop.
          • The shop is a steel building with a finished concrete floor and a paint booth for each unit.
          • The unit will be placed in the spray booth.
          • The booth will be opened at one end of the booth for makeup air.
          • The exhaust air will flow through an exhaust chamber at the other end of the unit.
          • For each unit, once the liner application operations are completed, the forced curing (drying) operations will immediately commence.

          Booth Exhaust Chamber

          Instructions:

          1. Closely read the required reading assignment from the textbook and the unit lesson within the study guide, and consider reading the suggested reading.
          2. Select the PBR evaluation document to be for only one of the following: (a) an aircraft manufacturing exterior coating paint booth, (b) a rail tank car interior lining process, or (c) a vehicle exterior coating paint booth. You will continue with this scenario selection for the remaining six units, to complete the entire document.
          3. Using APA style (title page, abstract page, body with level 1 headings, and a reference page) for a research paper, begin drafting a PBR evaluation document. You will add to this document in every subsequent unit with another prescribed level 1 heading, building out the entire document one section at a time.
          4. Make your Unit II work the first level 1 heading (center, bold) titled “General Considerations for Operation,” and describe the scenario that is presented above, while specifically describing the scenario that you selected (aircraft, tank car, or vehicle). While describing your scenario, you must include the environmental, health, and safety (EHS) implications of the work system while pulling from the textbook as well as any other relevant sources that are presented in the unit lesson in the study guide. In your description of the EHS implications of the system, be sure to discuss the natural and anthropomorphic variables causally related to outdoor air pollution. You are required to describe the scenario in at least 200 words (minimum). You may find it convenient to summarize the tabulated information in your General Considerations section of the permit for future reference throughout the rest of the course, but do not attempt to tabulate the information in the exact order as what is presented here (to avoid a high match in SafeAssign).
          5. Also under the first level 1 heading, present a box and line process flow diagram (PFD) drawing of the selected scenario. See the drawing on page 375 of the textbook as an additional example of a PFD if you need assistance understanding how to draw one; do not draw the same system that is provided on that page. Do not hand-draw this, but use the “insert” and “shapes” features within Microsoft Word to construct the PFD. Simple labeled boxes and lines are adequate for this preliminary work, so it is not necessary to present specific shapes in your PFD for your selected scenario.
          6. In your abstract section (page 2 of the document), write one or two sentences that reflect your work for this unit. We will be adding one sentence per unit to reflect our work as we go, with the final abstract length being about 8 to 10 sentences long.

          In following units (Units III through VII), the unit lessons will contain information related to the interior surface coating operation by means of practical mathematical calculation examples. Consequently, it is imperative that you read the unit lessons within the study guide in every unit, use the math calculation examples provided in each unit lesson, and consider the current (as well as previous) material from the textbook and the additional information cited and referenced in the study guide for every unit. This project will serve as a comprehensive demonstration of your applied learning of engineering air quality.

          Your completed mini project should be a minimum of one page, not counting the title page, abstract page, and reference page. You are required to use at least one outside source, which may be your textbook. All sources used, including the textbook, must be referenced; paraphrased and quoted material must have accompanying APA citations.

          Resources

          The following resource(s) may help you with this assignment.

          Submit Unit II Mini Project »

        • Item

          Bootstrap

          Loading...
        ×
        ###
        Close