Shoreline Stadium Case
The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on July 3, 2017, and be completed in time for the start of the 2020 season. A penalty clause of $250,000 per day of delay beyond April 3 is written into the contract.
Percival Young, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $3 million on the project. He also said if they were successful, the prospects of future projects are bright since there is a projected renaissance in building classic ball parks with modern luxury boxes.
ASSIGNMENT
Given the information provided in Table 6.3, construct a network schedule for the sta- dium project and answer the following questions:
1. WilltheprojectbeabletobecompletedbytheApril3deadline?Howlongwillittake?
2. What is the critical path for the project?
3. Based on the schedule would you recommend that G&E pursue this contact? Why?
Include a one-page Gantt chart for the stadium schedule.
Case Appendix
Technical Details For The Shoreline Baseball Stadium
For purposes of this case assume the following:
1. The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.
2. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.
3. Develop the model in MS project and answer questions in this case study. You must upload your MS Project file as well as a word file with answers to the questions.