THERE SHALL BE a calculation BEYOND SIMPLE MULTIPLICATION on this table PLEASE EXPLAIN YOUR ANSWER

profilebzstudent
please fill out the table and give an explanation for your calculations, 
 

 

 

Item

 

Immediate predecessor

 

Duration (weeks)

 

 

No. of resources

Level of Effort (number of workers X duration of work)

 

Labor cost

 

Material cost

 

Total cost

A

 

 

4

2 designers @ $1,600/person/week

 

 

 

$1,000

 

B

A

 

2

2 programmers @ $1,200/person/week

 

 

 

$2,000

 

C

A

 

4

1 programmer @ $1,200/week/person

 

 

 

$2,000

 

D

B

 

6

1 testers @ $1,000/week/person

 

 

 

$5,000

 

E

C,B

 

3

2 testers @ $1,000/week/person

 

 

 

$ 2,000

 

F

D,E

 

3

2 integrators @ $1,800/week/person

 

 

 

$1,000

 

Total

 

 

 

 

 

$13,000

 