Using PERT in Scheduling Projects (75 Points)

PERT is a scheduling system that is widely used in businesses to help organize and control the completion of a major project.  Table 1 lists the tasks, the time required to complete the tasks of the assembly of a particular product in the SmartView company, and the dependency among these tasks. 

Answer the questions, below. Please remember that any written part of your assignments must follow the CSU-Global Guide to Writing and APA Requirements

Table 1

Task

Time Required (Days)

Preceding Tasks

1. A

5

None

2. B

7

None

3. C

4

A

4. D

5

A, B, C, E

5. E

6

B

6. F

7

A, B, C, D, E

7. G

4

A, B, C, D, E

8. H

3

A, B, C, D, E, F, G

Using table 1:


The graphs that are featured are in the attachment.

 

  1. Choose the graph that is the closest to the table.

  2. In your selected chart, list all possible paths and determine the total completion time of each path.
  3. In your selected chart, determine the critical path and the earliest time needed to complete all tasks on the critical path.
  4. In your selected chart, determine a critical path for task D.