For an organization, the following project schedule is given. Assume that all times are in days.

Task

Predecessor

Normal Time

Crash Time

Crash Cost Slope

A

None

7

7

NA

B

A

3

3

NA

C

A

8

4

600

D

A

4

4

NA

E

B

6

5

600

F

C, D

2

2

NA

G

E, F

6

6

NA

H

F

5

3

400

I

G, H

4

4

NA

J

I

2

2

NA

In a 3- to 4-page Microsoft Word document, address the following:

  • Draw the AON project network using Microsoft Project, Microsoft Visio, or some other tool capable of creating such a network. Perform a critical path analysis for the network and calculate the ES, EF, LS, and LF times.
  • Calculate the slack time for each activity.
  • Identify the critical path.
  • Assume that the organization will receive a $400 bonus for each day the duration of the project is shortened. The organization is also responsible for paying the crash cost associated with shortening the schedule. To maximize the net profit, identify which task you should crash and by how much.
    • 10 years ago
    • 20
    Answer(3)

    Purchase the answer to view it

    blurred-text
    NOT RATED
    • attachment
      su_mgt3059_w2_a2_lastname_firstinitial.doc..docx

    Purchase the answer to view it

    blurred-text
    NOT RATED
    • attachment
      scheduling.operations_management.doc

    Purchase the answer to view it

    blurred-text
    NOT RATED
    • attachment
      mgt_3059_week_2_assignment_2_project_network_activity_with_bonus_1000.mpp
    • attachment
      mgt_3059_week_2_assignment_2_project_network_activity_with_bonus_1000.xlsx
    • attachment
      mgt_3059_week_2_assignment_2_project_network_activity_with_bonus_400.docx