Mangment exam(Essay)

profileSam's.Tech

Given the information bleow 

Activity

Description

Immediate Predecessors

Time (weeks)

1

Build internal components

-

2

2

Modify roof and floor

-

3

3

Construct collection stack

1

2

4

Pour concrete and install frame

2, 3

5

5

Build high-temperature burner

3

4

6

Install pollution control system

3

3

7

Install air pollution device

4,5

5

8

Inspect and test

6,7

2

Please fill in all the following blanks:

(1) Identify the Critical Path [removed] (in the format of ####, no space or any punctuations between activity numbers, e.g., 1457).

(2) The total project completion time is [removed]weeks.

(3)  If the required completion time is 15 weeks, calculate EF, LF, and total slack time for each activity. (note: ES and LS are not required in the table)

 

 

 

q2.

Provide an example of work breakdown structure and indicate what purpose WBS serves.

 

  Note:  Explain in 200 words or less. No structure drawing is required. Just describe it in your words. For example, 'pass a exam', could be divided into 'review the reading materials' and 'take quizzes'; then 'review reading materials' can be split into 'read slides' and 'read textbook'......